rmd walers can be seen in the background holding internal facade

RMD Megashor Facade Retention, Structural Propping and Needling.

This innovative temporary works design allowed the street to stay open and produced the maxiumum wind resistance.This architectural important building was retained on three sides. While a 13 metre deep excavation inside the footprint of external walls took place. Structural propping against the basement walls helped to support the facade walls. Two storeys were added to top of this iconic building. A dramatic increase in the size of this building while conserving the traditional look was a considerable acheivement. E P Rothwell & Sons Ltd are Members of the Temporary Works Forum (TWF)

If you have a temporary works project, please ring us on 01753-646012, to discuss a solution.