Facade Retention and Propping Portland Square

We were approached to design and erect the Temporary works on this exciting project. We created a temporary works design that used a structural Steel facade for most of the external support to the building this was supplemented by using RMD Superslim soldier raking props and a section of RMD megashor tower. Mabey mass 50 was used internally to support the load bearing walls However most of the temporary work design was the steel facade retention which was designed and fabricated in our yard and placed by our site team using 30 tonne to 50 tonne cranes Access was gained by using Cherrypickers and sissor lifts.

The new construction works were considered in our design and this allowed a fast track programme to be achieved. Most importantly the Facade of a beautiful was retained as the interior was modenised.

Please ring us on 01753-646012.