RMD Superslim providing a continous beam while also allowing new structure to proceed

RMD superslim beams internal Facade retention.

The permanent works design required the new steel frame to fixed against the existing facade, Our temporary works engineer designed a continuous RMD superslim waler with ninety degree brackets to allow for the steel columns to be fixed without the need for any adjustments to the walers. Saving both time and cost.

Design with the new construction in mind

We always consider the new construction in all our designs, The first image shows the pockets created against the wall which allows for installation of the new steel frame. Alshor plus supported the existing floors where the imposed loads were less challenging.

We also used Structural steel and maybey mass 25 props in the lower basement areas.