Shoring and Structural Propping Marlborough Art Gallery

Marlborough Art Gallery

Design

We were appointed to produce a Temporoary works Design, and then to install propping and shoring to secure this fine building which was partially occuppied as demolition and construction progressed.

Errection

RMD Superslim backpropping was installed on lower levels of the structure.An Alshor plus soffitt support system was then installed to allow demolition to commence. Because of concerns with the strength of existing walls EPR conducted pull out tests. And a monitoring system was installed.

Megashor propping supported the rear of the building, further shoring was fixed to external walls using mabey 160 raking props.

Propping to upper floors continued using a combination of Gass and Mabey mass 50,RMD super slim and alshor plus.

We are proud to have worked on this fine building.