Facade Retention Steel Frame, Structural Propping for ISG

Peterborough Shopping Centre

Design

ISG asked E P Rothwell to create a temporary works design for a steel frame and a Structural propping system. This needed to be done while the precinct remained open so the temporary works design had to account for this and allow for quick installation so causing the least distruption. We therefore fabricated the steel in our workshop in Staines and used bolt connections where possible to reduce hot works on site. As this was a large steel frame over eighty tons which was providing support throughout the precinct it was quite a challenge. We also fixed RMD superslim (Slimshore), Megashor and Alshor plus to provide support for the walls and floors to the mall. Maybey Mass 50 was used in basement areas. ISG were happy with our performance on this challenging contract.